Gunby Roundabout set for night-time improvements

Night-time resurfacing works to replace the worn-out road surface on each leg of Gunby Roundabout, along with a stretch of the eastbound A158, will start on Monday 9 September.

The total programme of works is expected to last for eight weeks, subject to suitable weather conditions, with the works being carried out in phases.  The closures will be in place from 7pm to 6am, Monday to Friday.

These works will inevitably cause some disruption, but we'll be doing everything we can to keep it to a minimum.Karen Cassar, Lincolnshire County Council

In addition to road closures at various points of the roundabout during the works, lane closures will also be in place on the dualled sections of A158.

Contractors will ensure access for emergency vehicles, residents and businesses will be maintained at all times, as far reasonably practicable.

Karen Cassar, assistant director highways, said: "Gunby is an essential part of the route to Skegness and the county's coast from the west.

"Over the years, the condition of the road surface at each of its legs has considerably deteriorated. So, once the summer holidays are over, we'll be rebuilding each leg of the roundabout so that people's journeys are smoother and safer.

"These works will inevitably cause some disruption, but we'll be doing everything we can to keep it to a minimum, including working overnight so that people using the roundabout in the day aren't affected."

Week 1 - week commencing 9 September

  • Two evening road closures of the B1196, starting Monday 9 September
  • Diversion route via B1196, A1104 and A1028
  • Three evening road closures of A1028, starting Wednesday 11 September
  • Diversion route via A1028, A16, A158

Week 2 - week commencing 16 September

  • Three evening road closures of A158 (western arm), starting Monday 16 September
  • Diversion route via A158, A16, A1028
  • One-evening road closure of Gunby Hall access on Thursday 19 September
  • One-evening road closure of the A158 westbound dual carriageway on Friday 20 September
  • Diversion route via A158, A52, B1449, A1111, A1104, A1028

Weeks 3-6 - Monday 23 September to Saturday 19 October

  • One-evening road closure of the A158 westbound dual carriageway on Monday 23 September
  • Diversion route via A158, A52, B1449, A1111, A1104, A1028
  • Four weeks of evening road closures on the A158 eastbound dual carriageway, starting on Monday 23 September
  • Diversion route via A158, A52, B1449, A1111, A1104, A1028
  • Please note that lane closures will be in place during the daytime
  • Three evening road closures at the Orby junction, starting on Wednesday 16 October
  • Diversion route via C541, A52, A158

Published: Wednesday 14th August 2019


By submitting your comment you are confirming that your post meets the site terms & conditions. Posts which do not meet the terms & conditions may be subject to moderation or removal.

Your comments may take a few moments to appear in the main comment box above.

Share |

Related Articles

Article Tags

»  September
»  Road
»  Closures
»  Route
»  Diversion
»  Works
»  Starting
»  Carriageway
»  Roundabout
»  Closure
»  Gunby
»  A158

Article Links


Although we try to check the suitability of each of our external links, we cannot be held responsible for the content of external links.